Planning Board approves National Grid substation expansion and School Street commercial development
Board grants site plan, stormwater, and special permits for the 599 Spring Street substation and approves contractor bays on a School Street lot; continues the 61 Railroad Street hearing.

Corrected on October 27, 2026. How we correct errors
The Winchendon Planning Board unanimously approved the site plan, stormwater management permit, and special permit for the National Grid substation expansion at 599 Spring Street 58:56. The project, which adds a transformer to increase reliability and capacity for the aging substation, is scheduled to commence in February and be completed in Spring 2029 55:59. The board also unanimously approved the site plan for a four-building commercial development — contractor bays — on a School Street lot with no street number yet, across from 703 School Street 106:16.
- Continue public hearing for 61 Railroad Street to November 17th — Unanimous 11:35
- Close hearing for 599 Spring Street — Unanimous 50:43
- Approve site plan, stormwater permit, and special permit for 599 Spring Street — Unanimous 58:53
- Close hearing for the School Street contractor bays — Unanimous 104:28
- Approve site plan for the School Street contractor bays — Unanimous 106:16
- Motion to adjourn — Unanimous 107:05
The 599 Spring Street hearing, continued from previous meetings, focused on 18 waiver requests from the applicant, National Grid, represented by Joe Duquette of Bowditch & Dewey 12:44. National Grid project director Nui Huang said the upgrade is designed to be paid for by distributed-generation customers such as solar projects. Ratepayers across Massachusetts, not only Winchendon's, pick up a portion of the cost at first, which he put at about 5 to 10 cents per customer, and it is credited back as those generators connect 22:40. The board denied waivers 11, 12, and 13 regarding consent to entry and easements, but imposed conditions allowing the town to accept photographs in lieu of direct inspection for restricted areas 52:29. Waiver 18, a sweeping request for additional zoning bylaws, was also denied 54:33.
For the School Street lot, Wes, the applicant's engineer from McCarty Engineering, presented revised plans for four buildings instead of the three the Zoning Board of Appeals approved: two smaller buildings first, meant for rent to small contractors such as a plumber or an electrician, and a second phase still to be decided 61:44. The town's peer reviewer, Tighe & Bond, confirmed that its stormwater management comments had been addressed 64:02. The board granted waivers for lighting requirements, tree identification, and stormwater pipe diameter, and also waived the requirement to fence the detention basins after a board member said a chain-link fence would make the lot "look like a prison"; the board said it can revisit fencing if problems such as debris come up 94:32.
The board imposed several conditions on the School Street approval, including the submission of signage and building elevation details for approval prior to occupancy 99:53. The applicant must also record stormwater easements to provide the town with access to stormwater BMPs 102:59. The hearing for 61 Railroad Street was continued, at the applicant's request, to the November 17th meeting 11:27.
- Continued the public hearing for 61 Railroad Street to the November 17th meeting 11:27.
- Approved the site plan, stormwater management permit, and special permit for the National Grid substation expansion at 599 Spring Street 58:56.
- Approved the site plan for the contractor-bay development on School Street 106:16.
- Motion to adjourn was made and seconded 107:05.
- The existing substation equipment is over 60 to 70 years old.
- The original ZBA approval was for three 7,500-square-foot buildings.
- Buildings of 5,000 square feet or under do not require sprinklers, but the board will condition approval on the building inspector and fire department determining the need for sprinklers during permit review.
- The School Street site is approximately 20 to 25 acres, with about 5 acres of disturbance planned.
- The detention basins on the School Street lot are supposed to drain within 72 hours of any rain.
- The National Grid project is scheduled to commence in February and be completed in Spring 2029.
- The 61 Railroad Street hearing was continued to the November 17th meeting.
A name wrong in this story? Tell us
A figure wrong in this story? Tell us