BOS Hear Updates on Mabardy Capping, Projects Around Town

Water, Ash and Spring Streets intersection Photo from Google Street View
Water, Ash and Spring Streets intersection Photo from Google Street View

Cet article est en cours de traduction ; le voici en anglais.

Listen · Read aloud; the words light up as you listen

At their meeting on Monday, July 13, the Board of Selectmen heard updates from the Town Manager and DPW Director about a number of projects happening around Winchendon.

Town Manager Bill McKinney gave the Board a timeline for the Mabardy landfill capping project off of River Street which has continued for several years now and which is reportedly close to its completion. Mr. McKinney said that W.L. French, the firm doing the work on the site, should now be finished bringing in COMM97 fill for the capping. That should have finished by June 30, he said.

"It was asked when they are supposed to complete, and that date they've given me is November 17th," Mr. McKinney said. "So according to their schedule, which was as of June 30th last week, they would have drilled the gas venting wells for the rest of the month. They'll be installing the bedding layer, and then liner installation will be going on around the same time. The geocomposite installation should be done by August 25th. The diversion berm installation should be done by October 27th, the topsoil installation November 10th, and the hydro seeding November 17th. So this is something we can put on the website as well to keep people informed of what's happening."

(The Mabardy landfill reports are found, rather counter-intuitively, under the Zoning Board of Appeals tab on the town website--and Clyde the AI does not tell you this. The Mabardy page is at https://www.townofwinchendon.com/418/Mabardy-2021-to-2026-Reports , for those looking for it.)

Later in the meeting, Department of Public Works Director Patrick Wood was asked about a number of ongoing projects in town. Residents have noticed the street sweeping going on, Mr. Wood said. "There is a lot to it, so he's taking the time to show them how to operate the machine, where to hook up the water, where to dispose of everything. I think they started on Elmwood. They did some of Maple last week, and they're going to be targeting this week, they're going to get down by the bridge by Beech Street, get that cleaned up, and they have their routes that they're going to be doing throughout the rest of the year. It's a long process. I will share with you same thing that they shared with me, that the bridge in front of Beech Street constantly gets sand. So we we recognize that we're going to do it once, might look good for a few days, after a couple rainstorms, we might go back to looking what it is. We'll come back to it as soon as we can, but we do want to do the street sweeping around town. Makes it look look nice, and we also want to restripe our center lines and our fog lines this year as well. The roads need it, and they definitely need to be swept before we invest some money into getting the line stripes."

Work is proceeding with the dangerous meeting of roads at the Ash Street, Water Street, and Spring Street intersection. The DPW wants to be sure that the positioning of lines and stop signs makes the best sense before they're put down permanently. "It's going to end up having--I don't know if you can picture it--but I think the biggest change is that there's going to be a right-hand turn in a straight lane as you're coming off of Spring and heading down Ash, so it the whole idea is to just channelize drivers and keep it as narrow as we can to slow down speeds through the intersection," he said.

Board Chair Andrew Beauvais said that he thought the best solution for that intersection would be a rotary, or a roundabout as Mr. Wood said engineers call them. Mr. Wood agreed, saying, "There's a huge difference, but yeah, there there are a lot of benefits, and I think the biggest pushback to them is just that they're new, and people, we're all hesitant to new things, but the data is out there, and the data supports that they do a lot of traffic calming. It reduces queues. It creates gaps in traffic so that people can get out. Collisions are a lot less. T-bones aren't a thing with roundabouts. So someday, if we ever need it, we can look into it." They do take up a lot of real estate, he said, being at least 15 to 20 feet in diameter. "Otherwise, we'd probably see them everywhere."

Mr. Beauvais said that a roundabout there would help beautify that "gateway" into town.

Mr. Wood also said, "The sidewalk project in front of the school, it's going on right now at G.A.R. Park. We're putting sidewalks around the edges of G.A.R. that don't have sidewalks. We're extending sidewalks from the school up Murdock, and then we're going to jump over, I think it's Pearl Street to Jackson Ave, where there are some missing sidewalks as well. So all of Jackson Street will have new sidewalks too, and this was part of the Complete Streets grant that we received two years ago."

Board member Erika Eitland said that she felt Water Street needed a sidewalk, because people come down High Street and are looking to connect with the walking trail, and they can no longer walk over the Front Street Bridge.

Mr. Wood said, "We can look at that. We're always trying to fill the gaps in the sidewalk network. I'm not a huge fan, I was telling Bill this earlier, I'm not a huge fan of adding a ton of sidewalks around town. I'd rather fix up the sidewalks that we have. So it should be noted that there's no town funds being put into the new sidewalks that are going on at G.A.R. Park and Jackson Ave. That was a gift from Complete Streets for us. Second to that is filling in gaps in our sidewalk connectivity. So that would be something that we'd be very interested in doing."

Finally, Mr. Wood said, the Beech Street Project is about 95 percent done. "We've done our punch list walk through with the contractors. We've spoken with residents that have had concerns, and I will say, all in all, the residents had concerns about their private property, we've been addressing it with them. Outside of that, it's been a pretty successful project. The water line was put in, the sewer line was realigned, and the drainage system was fixed because that was a notorious flooding area. And it all came in well under budget and under schedule.

"So the the remaining money that we have, we used to binder pretty much the entire road, and we're going to see if there's a possibility of putting something more permanent on the sidewalks that were disturbed. Because right now you'll notice that it's just gravel. We're going to see if there's an option to get them either bindered with inch and a half asphalt, or maybe some asphalt grindings, something to that effect. And we're gonna redo the parking lot that's on Beech Street because they had to raise the road a little bit to accommodate all catch basins. There's some ponding on there. You probably noticed that in heavy rains now. So they're going to send us a change order and an estimate to level it out more, and we'll end up with a nice brand new parking lot too."

A name wrong in this story? Tell us
A figure wrong in this story? Tell us
Who is in this picture?help name the people in it

Know someone in the picture? Sign in to tell the editors — no password, a link by email.

Comments

0 so far
No comments yet. Be the first.

Sign up to comment

Your name shows with your comments; your email never does. We send one email — tap it and you are back here, signed in, ready to comment. No password.

Comments from signed-up readers appear at once. No links. Off-topic, spam and abusive comments are taken down. Already signed up? Sign in.